The concrete contractor has completed all foundation walls. They are currently working on the curb along Locust Street. Now that the foundation walls are complete, the general contractor will begin grading the site. It will appear that more work is going on now, because everything that has been done so far is underground! Storm sewer, foundation walls, stone, etc. all takes a significant amount of time to install.