Thursday, August 21, 2008

Construction Progress

The contractor has installed new curb along 2nd Street. An asphalt patch still needs to be done in front of the curb and will be done soon, but in the meantime, the spots on the East side of 2nd ARE open. HOWEVER, since the spots are slightly narrower, please be conscious of the back end of your car sticking into the lane of traffic. Park at your own risk.

The next items on the list of work include the foundations for the dumpster enclosure and the retaining wall along Palmer Ct. Work is proceeding forward according to schedule!