One Week Look Ahead

The contractor has continued removing the pavement from the parking lot. This has turned out to be quite the task! Those concrete walls that were about 3' high lining Palmer Court had a foundation 4' x 4'!!! There are some big holes in the lot now. Plus we found the basement walls of the old building that used to be around. It's been quite interesting.

The contractor will continue pavement removal and then start leveling out the lot. Storm sewer removal and installation will follow soon after that.

I will be out of the country next week, so Robert Hallock will be filling in for me. He'll be in the field office if you need him.