The contractor has installed new curb along 2nd Street. An asphalt patch still needs to be done in front of the curb and will be done soon, but in the meantime, the spots on the East side of 2nd ARE open. HOWEVER, since the spots are slightly narrower, please be conscious of the back end of your car sticking into the lane of traffic. Park at your own risk.
The next items on the list of work include the foundations for the dumpster enclosure and the retaining wall along Palmer Ct. Work is proceeding forward according to schedule!
FIELD OFFICE
213 E. Locust Street; 815-756-2319
Thursday, August 21, 2008
Monday, August 11, 2008
Friday, August 1, 2008
Storm Sewer Installation
Elliott & Wood began storm sewer installation earlier this week. This operation should take us through to the end of next week.
The entire parking lot is made of permeable pavers. That means that it's going to be brick that drains water. Underneath the bricks is a layer of stone that the water can drain through. 4" pipe underdrains will be placed sporadically through out the parking lot to drain all the water permeating through the pavement to the structures and to the storm sewer main. It's a very interesting process. So instead of water pooling on the surface, it drains right through. You can see an example video on www.perviouspavement.org, then click on "NEW Video & TV News Reports on Pervious Concrete".
Monday, July 28, 2008
2nd Street Closed to Vehicles Today
2nd Street will be closed today until early afternoon to all vehicles. The contractor is installing a water service across the street (the main is on the west side of 2nd). Pedestrians are still able to use the sidewalk. The road will be reopened by the end of the work day.
Thursday, July 24, 2008
Done with the unexpected...hopefully
Well, after a wonderful week in Spain, I came back to find out that there were more basement foundation walls than expected. As of yesterday (Wednesday), we've removed all that needs to be removed. What we did was cut down the walls to a foot below subgrade (subgrade = the bottom of everything new that is being put in).
Now that all of that is done, the contractor is going to continue with storm sewer removal and relocating the existing fire hydrant. Storm sewer installation will start soon and once that is complete, site grading will begin.
Now that all of that is done, the contractor is going to continue with storm sewer removal and relocating the existing fire hydrant. Storm sewer installation will start soon and once that is complete, site grading will begin.
Friday, July 11, 2008
One Week Look Ahead
The contractor has continued removing the pavement from the parking lot. This has turned out to be quite the task! Those concrete walls that were about 3' high lining Palmer Court had a foundation 4' x 4'!!! There are some big holes in the lot now. Plus we found the basement walls of the old building that used to be around. It's been quite interesting.
The contractor will continue pavement removal and then start leveling out the lot. Storm sewer removal and installation will follow soon after that.
I will be out of the country next week, so Robert Hallock will be filling in for me. He'll be in the field office if you need him.
The contractor will continue pavement removal and then start leveling out the lot. Storm sewer removal and installation will follow soon after that.
I will be out of the country next week, so Robert Hallock will be filling in for me. He'll be in the field office if you need him.
Thursday, July 3, 2008