FIELD OFFICE
213 E. Locust Street; 815-756-2319
Tuesday, September 23, 2008
Thursday, September 18, 2008
LOCUST STREET CLOSURE
Please be advised that Locust Street will be closed between 2nd and 3rd Streets the week of September 21. There will be access to the NB&T parking lot, and 2nd and 3rd Streets will NOT be blocked or closed in anyway.
Construction Progress
The concrete contractor has completed all foundation walls. They are currently working on the curb along Locust Street. Now that the foundation walls are complete, the general contractor will begin grading the site. It will appear that more work is going on now, because everything that has been done so far is underground! Storm sewer, foundation walls, stone, etc. all takes a significant amount of time to install.
Tuesday, September 2, 2008
Concrete Foundation Walls
The concrete subcontractor has been working on the foundation walls for the seat wall along Locust, the retaining wall in Palmer Court and the dumpster enclosure wall. Once this work is done, masonry installation will begin for these three structures.
Site grading should begin within the next week or two.
Site grading should begin within the next week or two.
Subscribe to:
Posts (Atom)